Traffic Impact Assessment, Pavement Impact Assessment, Over Size Over Mass Strategy

Bremer Battery Project – Battery Energy Storage System (BESS)

The Bremer Battery Project is an 850MW/3400MWh Battery Energy Storage System (BESS) proposed by Libra Energy at Lower Mount Walker, west of Ipswich. The project will help deliver a safe and reliable energy grid for Queensland. It will support efficient energy use and energy security for households and businesses across the State.

Marvel Engineers was engaged through Xenith to provide the transport planning inputs for the project’s development application and construction planning. Our scope included:

  • a Traffic Impact Assessment (TIA) covering site access, car parking, operational and construction traffic, and road safety.
  • a Pavement Impact Assessment (PIA) to understand the effect of construction traffic on Rosewood–Warrill View Road, a state-controlled road.
  • an Over Size Over Mass (OSOM) Strategy for delivering the project’s largest components from the Port of Brisbane to site.
Challenges

Building a battery of this scale means moving some very large equipment along public roads. The project requires four transformers, each weighing more than 150 tonnes. They will be carried on a specialised transport combination over 70 metres long. Hundreds of battery units and inverters will also be delivered during construction.

The route from the Port of Brisbane to site travels along motorways, highways and rural roads. Along the way, it passes beneath bridges with limited overhead clearance. It crosses many bridges whose capacity for heavy loads needed to be checked. It also negotiates tight roundabouts and intersections. The final approach is along Rosewood–Warrill View Road, a 100km/h rural arterial road with narrow lanes and shoulders.

Adding to the complexity, a haulage contractor had not yet been appointed. This meant the final vehicle configurations, dimensions and masses were not confirmed while the strategy was being developed.

Outcomes

Marvel took a staged approach, with each assessment building on the last.

The TIA confirmed a safe site access arrangement, including an upgraded intersection treatment at Rosewood–Warrill View Road. It also showed that operational and construction traffic would not significantly affect the surrounding network. The PIA then confirmed that construction traffic would add less than 5% to background pavement loading. As a result, no pavement contribution or offset works would be required under TMR guidelines.

For the OSOM Strategy, the team adopted representative transport configurations based on supplier information and comparable transformer movements. This allowed planning to progress before a haulage contractor was on board. The team then:

  • reviewed overhead clearances along the route and identified alternatives where structures were too low.
  • completed swept path assessments at key intersections and roundabouts, identifying where controlled kerb overrun or temporary removal of signs would be needed.
  • reviewed serious heavy vehicle crash history along the full route
  • set out a preliminary traffic management and permit pathway.


We also engaged early with TMR’s Heavy Vehicle Projects, Metropolitan District and Structures teams. TThis led to TMR completing a preliminary structural assessment of the route for the transformer, battery and inverter vehicle configurations. The assessment identified the structural travel restrictions likely to apply.

Benefits of the solution

Engaging TMR early gave Libra Energy visibility of the key structural risks on the route well before any permit applications are lodged. TMR’s preliminary feedback on vehicle loading also gives the future haulage contractor a clear target for configuring the transport vehicle. This improves the likelihood of a smooth permit process.

Together, the three assessments provide a consistent, evidence-based transport case for the project. The OSOM Strategy gives Libra Energy and its logistics contractor a clear roadmap. It sets out the constraints to manage, the approvals required and the information needed to finalise the movement plan. Identifying these risks early, when they are easiest and most inexpensive to address, helps protect the project’s construction program.

Reach out if we can help with traffic and transport planning for your next energy or infrastructure project.

Image courtesy Libra Energy

Utility Services Coordination

We know that utilities are often one of the most high-risk activities for any project budget and program. Our team has an extensive background modelling new and existing utilities, and coordinating utility designs to avoid clashes with other project elements. We also have established relationships with all utility providers in Queensland which means that we can commence consultation immediately and minimise program risks.